Tooele, Utah · Subdivision

$66,000,000, 220-lot civil subdivision with five community shared buildings.

CSC managed full civil delivery for this phased subdivision, including grading, utilities, roads, and stormwater systems, with shared community facilities and amenities.

Project Overview

The Tooele subdivision encompasses 220 residential lots and five community shared buildings. CSC oversaw all civil work including grading, underground utilities, stormwater drainage, asphalt, curb, gutter, and sidewalks. The phased approach accelerated lot releases while maintaining QA/QC standards for long-term asset performance.

Value
$66,000,000
Lots
220 residential
Community
Five shared buildings
Delivery
Phased civil & infrastructure

Scope

  • Civil works: grading, utilities, drainage, and retention
  • Roads, asphalt, curb, gutter, and sidewalks
  • Community buildings and shared amenities

Role

  • Owner’s Representative and field coordination
  • Municipal coordination, permitting, inspections
  • Schedule, quality, safety, and cost control

Execution

  • Phased infrastructure for accelerated lot turnover
  • QA/QC standards ensuring long-term performance
  • Stakeholder and contractor management